| If you have a solar load or wind of 2 MW or less based on your annual maximum kW demand, you may be eligible to send excess KWhrs back to PSE&G for a credit.
In order to take advantage of this offer, you must complete the following process for approval:
-
Complete an interconnection agreement and send to PSE&G at the address listed below.
-
PSE&G will review your equipment against local circuits to ensure compatibility.
-
Once your equipment has been verified, you can install the equipment
-
Before you may operate the equipment, a local electrical inspection is needed.
-
We need to receive the result of the inspection prior to changing the meter equipment.
-
PSE&G will change the meter equipment so we can track the usage and apply credits.
Equipment is broken into three levels:
|
Level
|
Specifications
|
Response
|
Cost
|
|
1
|
- The facility is inverter-based
- The facility has a capacity of 10 kW or less
- Complies with UL 1741 and IEEE 1547 design standards
|
Initial response within three business days, and an additional 10 days for engineering review |
No fee |
|
|
- The facility has a capacity of 2 megawatts or less
- Complies with UL 1741 and IEEE 1547 design standards
|
Initial response within three business days, 15 days for engineering review |
$50 plus $1 per kW of installed capacity |
|
|
- The facility has a capacity of 2 megawatts or less
- Does not meet the technical requirements for level 1 or level 2
|
Initial response within three business days, 15 days for engineering review |
$100 plus $2 per kW of installed capacity |
Order processing:
PSE&G Construction Inquiry
750 Walnut Avenue
Cranford, NJ 07016
Phone: 1-800-722-0256, Option 3,
Fax: 1-908-497-1762
Email: cimail@pseg.com
Technical assistance:
Jim Calore
PSE&G
80 Park Plaza, T12
Newark, NJ 07102
Phone:973-430-6628
Fax: 973-621-8410
Email: james.calore@pseg.com
For more information, please visit njcep.com.
|